Earned Value Calculation Walkthrough

Table output Has example

Measure progress against cost and schedule.

The Open buttons send the prompt text as currently shown below to that site only when you click. Fill in the placeholders first.

Rate this prompt

Loading ratings…

Walk me through earned value for my project. Budget at completion: [BUDGET_AT_COMPLETION]. Planned percent complete to date: [PLANNED_PERCENT]. Actual percent complete: [ACTUAL_PERCENT]. Actual cost to date: [ACTUAL_COST]. Weeks elapsed and total weeks: [WEEKS].

Compute with my numbers and explain each result in one plain sentence:
- Planned value PV = planned percent x budget.
- Earned value EV = actual percent x budget.
- Cost variance = EV - AC; schedule variance = EV - PV.
- Cost performance index = EV / AC; schedule performance index = EV / PV.
- Estimate at completion: EAC = BAC / CPI if current efficiency continues, and EAC = AC + (BAC - EV) if the rest goes to plan.
- Estimate to complete and variance at completion.

Output format: a calculation table (Measure | Formula | Value | Meaning: over or under budget, ahead or behind), then a range for the final cost from the two EAC cases, three recovery options with trade-offs, and a stakeholder summary of about 100 words. Add cautions: percent complete is a judgment, EV ignores quality, and indices mislead early in a project.

Fill in before use

Optional: type your details and the prompt above updates. Nothing is saved or sent.

Replace each bracketed placeholder with your own details, then paste into Any AI or another assistant.

See an example result (fictional data)
Budget at completion 200,000. Planned 40 percent complete, actual 35 percent complete, actual cost 90,000.
PV = 0.40 x 200,000 = 80,000. EV = 0.35 x 200,000 = 70,000.
Cost variance = 70,000 - 90,000 = -20,000 (over budget).
Schedule variance = 70,000 - 80,000 = -10,000 (behind).
CPI = 70,000 / 90,000 = 0.78. SPI = 70,000 / 80,000 = 0.875.
EAC if current efficiency continues = 200,000 / 0.78 = 256,410. EAC if the rest goes to plan = 90,000 + (200,000 - 70,000) = 220,000.
So expect between 220,000 and 256,000. Percent complete is a judgment; verify it before reporting.

Illustrative only, made-up data. Your results will differ and must be reviewed.