Sprint Planning Agenda and Capacity Check for Jira

Table output Has example

Plan a sprint with realistic capacity and a clear goal.

The Open buttons send the prompt text as currently shown below to that site only when you click. Fill in the placeholders first.

Rate this prompt

Loading ratings…

Prepare sprint planning for [TEAM_NAME]. Sprint length and dates: [SPRINT_DATES]. Team members with planned days off: [TEAM_AVAILABILITY]. Average velocity of the last three sprints: [VELOCITY]. Candidate stories at the top of the backlog with sizes: [CANDIDATE_STORIES]. Focus factor to use: [FOCUS_FACTOR].

Compute capacity with arithmetic: available person-days times the focus factor, for example a team of 5 over a 10-day sprint with 4 person-days off is 5 x 10 - 4 = 46 person-days, then times the focus factor. Compare with the velocity-based range. Propose a sprint goal in one sentence, select stories that fit the lower end of the range, flag stories that are not ready, and list dependencies that could block the sprint.

Return a 60-minute agenda with timings that add up, the capacity table, the proposed sprint backlog in priority order, a risk list with one mitigation each, and the questions the team must answer before committing. Velocity is a planning aid, not a target to push.

Fill in before use

Optional: type your details and the prompt above updates. Nothing is saved or sent.

Replace each bracketed placeholder with your own details, then paste into Any AI or another assistant.

See an example result (fictional data)
Invented team of 5, 10-day sprint. Planned days off: 4 person-days. Available = 5 x 10 - 4 = 46 person-days. Focus factor 0.7 (to confirm): 46 x 0.7 = 32.2 effective days.
Velocity of last three sprints: 28, 34, 31 points; average = (28 + 34 + 31) / 3 = 31. Range 28 to 34.
Proposed commitment: 28 points (the lower end), because one person is away for the first four days.
Sprint goal: Customers can pay by card at checkout.
Not ready: two stories lack acceptance criteria; hold them in the backlog.
Risk: the payment provider sandbox may be slow to approve test accounts.

Illustrative only, made-up data. Your results will differ and must be reviewed.